CSR projects for FY 2020-21

Activities
  1. Construction of Boundary Wall
    The work order awarding process got delayed due to open tendering and limited no of participation
    and cost estimation. Work is in progress and will be completed by 31.10.2021.
  2. Street light solar project Phase-I (Palatana to Khilpara)
    Implementation partner is M/s EESL ( Government of India) .The work was delayed due to supply of materials and logistic to be Tripura site. Total 426 nos of poles were to shipped from MP to Tripura along with consumables. Work is in progress and will be completed by 30.06.2021
  3. 01 nos of Additional MHU for Tripura any district/blocks
    The work order awarding process got delayed due to open tendering. Work is in progress and will be completed by 21.01.2022.
  4. 02 nos Life support Ambulance Van
    Work delayed due to supply of materials and logistic to Tripura site. Work is in progress and will be completed by 31.10.2021.
  5. Phase -II solar street project
    Same as at Sr. No. 2 above
  6. Footbal tournaments at Sepahijala Distict
    The said tournament has been rescheduled due to on-going ADC election citing law and order problem. Now, it scheduled to be held in the month of June/July 2021 provided COVID situation gets normal.
  7. Fishery Development (Rural poverty alleviation)**
    Work is in progress