Milestone – Construction of Stack - I

 

Milestone – Construction of Stack - I 

Construction of Main Stack-1 base concrete was started on 12 Apr 2010 and completed on 13 Apr 2010. Total volume of concrete was 694 cum and carried out in single pour.

 

 

 

 

 