Implementation Schedule

Print

Generation Project :

The Project would be commissioned in 45 months from the issuance of Notice of Award (NoA) to EPC Contractor. The first unit would be commissioned in 42 months and the second unit would come on stream in 45 months. Since NoA to the EPC contractor was issued in June 2008, the first unit of the Project is expected to be commissioned in December 2011 while the second unit would be commissioned in March 2012

The commissioning of the associated transmission system from the project site to Bongaigaon in Assam would be aligned with the commissioning of the first unit of the Project

Expected timelines for achievement of key implementation milestones are as follows:

Table 28: Project Timelines :

ActivityTime-frame
Issue of NOA to EPC contractorJune 2008
Payment of Mobilization Advance to EPC ContractorAugust 2008
Commencement of Civil WorksOctober 2008
Receipt of GT at Project locationDecember 2010
Completion of Civil WorksJanuary 2011
Receipt of HRSG at Project locationMarch 2011
Erection of GTApril 2011
Erection of HRSG – Unit IMay  2011
Erection of HRSG – Unit IIAugust  2011
Targeted Commissioning of 1st UnitDecember 2011
Targeted Commissioning of 2nd UnitMarch 2012
   
OTPC has already finalized an extensive contractual structure for implementation of the Project within the envisaged cost & timelines. This contractual structure would ensure bankability of the Project from the lenders’ perspective.

Transmission line:

PGCIL, as Project Management Consultant (PMC) for the Transmission System, would oversee implementation activities by the Project contractors and ensure coordination between them. The presence of PGCIL as PMC mitigates risks associated with delays in Project implementation due to inadequate coordination between the Project contractors.The implementation schedule of the two projects would be synchronized to avoid any mismatch in commissioning.

 